Since Hurricane Milton, cable TV service is unavailable, but streaming TV is available. Please inquire if you have any further questions about this down amenity.
Please note that Concrete Repairs on floors 1-10 start Monday 10-27-25 and will be done around 12-1-25. Painting will start 11-17 and will be done around 12-1-25.
Waterproofing will start 12-1-25 and will be done around 12-8-25. Railing paint will start 12-8-25 and will be done around 12-15-25. Punch out 12-15-25 and will be done
around 12-18-25. Demobilize 12-18-25 and will be done around 12-22-25. Access to condo’s may be needed.
Please understand that the work will be noisy at times and that some areas of the building may be off limits to guests for short periods of time. Guests are required to show a photo ID and credit card upon check-in. Please note that all Special Requests are subject to availability and additional charges may apply.